MIAs at BMA Daunia and BMA Blackwater

Client: Downer EDI Mining
Contract value: $1,500,000 (combined)

Construction of a Mining Industrial Area (MIA) at both BMA’s Blackwater and Daunia open cut mines. These two projects were constructed for Downer EDI Mining in their capacity as contract miner. The works involved construction of a new Heavy Vehicle (HV) Workshop, HV Wash Bay, Jacking slab and various other ancillary structures. During the course of the project approximately 1000m³ of concrete was poured at each job.

Scope of works

Set out, steel fixing, formwork, HD bolts, concrete place and finish.